Contractual Issues with 485

First Published Wednesday, 20 July 2005 Last update 12 Jan, 2007 at 18:25:08

C O N T E N T S

Products
What we have to offer..

Order Full version NOW
Unfortunately in light of the fact that only a small number of SCLA copies have been sold, I have to increase the price of the software.  This software is now $30 hopefully I will be able to make suffucient money to support Vista..

This software, can save you many hours in testing serial links. For a professional approach use the detailed results in your commissioning reports.

LATEST NEWS

The SmartBay product range has been released Contract I.T. is going to bring Cabling Certification found in IP networks to CCTV networks.

CUSTOMER COMMENTS

I work in the oil and gas industry doing automation engineering and installation. I will use the software to setup and test radio links for data communications to the various oil and gas fields.”
Wes Sutton
Marathon Oil Company


The application we are using the program for is to check the character delay and loss rate over an Ethernet/TCP tunnelling system.”
Dr. Chris Clotworthy
Senior Design Engineer
Smart Light Devices Ireland

Contract I.T. Sincerely recommends NOT using Internet Explorer, we feel that you will be much safer if you switch to another browser. Contract I.T. recommends you use Firefox you can download it here. Or if you would prefer to check our recomendation google this topic

Contractual Issues whith IEC485(RS485)

Multidrop in contrast to point to point IEC485 networks are not trivial to implement. There are many engineering factors to take into account. If anyone involved in a project mentions RS-485 then it is imperative to initially ascertain that they infact refer to IEC485 which is the standard.

  1. Equipment compliance.
  2. Equipment interoperability.
  3. Cable requirements.
  4. Network Termination.
  5. Network Biasing.
  6. Baud Rate
  7. Surge Suppression.

 

1. Equipment compliance.

In order to ensure point 1 is met, It is best if the equipment is independantly certified to meet IEC485 on some commercial equipment the manufacturer will have allready done this.

2. Equipment interoperability

A Factory Acceptance Test Plan (F.A.T. plan) should incorporate a test that covers interoperability of the IEC485 equipment at the electrical layer with special notice given to framing errors.

3. Cable requirements.

Underground cable should be gel filled, above ground cable that is exposed should be UV stabilized, Arial cables should be supported. In general good cabling practices should be employed. If surge suppression is an issue cable paths should be sufficiently separated. There is no point have 3KV of opto isolation if your 300V rated insulation is the only physical barrier between the cable and the protected environment. Obviously cable with transmission characteristics that suit a differential mode communications transciever should be used.

4. Network Termination.

This will be determined by the cable characteristic impedance, usually a resistive element (resistor) is sufficient however capacitors may also be needed to tune the bus to the best state, the use of a CRO will help determine the best values to minimise overshoot and ringing of the bus and also reduce to a minimum the load placed on the transmitter.

5. Network Biasing.

Is outside the scope of this simple document, suffice to say it requires investigation when designing a 485 network.

6. Baud Rate.

485 is not like ethernet there are no pre determined speeds at which it is to operate, so one party’s 485 network may be 20 times faster than anothers and result in interoperability issues. If bad design prevails this will be picked up when the F.A.T. Plan is followed. (as a note I’ve also used 10/100 fibre optic GBICs that will not communicate with pure 100 GBICs both from HP), (I’ve also seen 100 GBICs from HP indicate a LINK when connected to 1000 GBICs now I suppose that technically there is a link present but no data is going to traverse that link while the GBIC mismatch exists).

7 Surge Suppression.

Is almost allways overlooked, sometimes it may be asked during a project to supply a letter stating that your equipment is surge protected. BEWARE this is basically stating that if there is any electrical disturbance onsite that damages your equipment you will warrant it. 485 is long distance communications from a surge point of view. There will be surge protection issues in most installations. The cost of a solution to these surges may range from $100 for opto isolation to $200,000 dollars for lightning towers and earthing mats. From a technical point of view there are two tasks Isolate and Shunt the surge to earth. Make it difficult for a surge to get into your equipment and then give the surge an alternate path. Use Mulit stage surge protection such as Avalanche Diodes, Metal Oxide Varistors, Gas Arrestors and Opto Isolation. I do not recomend Polymeric Positive Termperature Coefficient Resistors for current limiting in surge protection.

     